Monday, August 5, 2013

Down to the Details........

    There are many small details that our work crew is putting together to get this building done.   We were very disappointed to find out that the building wouldn't be (completely) ready for any of our summer groups.  We are also very thankful that they all understood and helped us help them make thier time here a success!


  All of the stud walls are up and most of the electrical circuits have been ran.  We are now working on a few smaller projects as well as dry walling the hall, bathrooms, and small meeting room.

Here's a couple pictures of the dry walling progress.
  This is the mens bathroom.  You can tell because the set of pipes in the far corner are for the urinals. The door to the right is the entry door.







This is the women's bathroom as you come in from the hallway.  As you can see we're in the middle of mudding this room.  The stalls are on the opposite wall pictured here.






This is the rock wall that we are currently putting up.  We got this wall from a High school near Parma Michigan about 2 years ago.  It was a great blessing and it's nice to see it out of storage and getting set up.  This picture was taken on a scaffold about 30 ft in the air.  




This is one of the two Septic tanks we are having installed for the new gym.  Becker and Scrives is the local concrete company and they do some pretty excellent work!  








 Don't let the picture fool you,  this tank is quite large and very heavy.  So heavy, in fact, that they can only carry one at a time with thier truck.  This system will feed directly into our existing septic field that is in the background.  We also use it as our paintball course.